Hazelmere Dam wall upgrade is back on track with the return of Group Five

Delayed construction work to raise the Hazelmere dam wall has finally resumed, with Water and Sanitation Minister Senzo Mchunu admitting on Saturday he was embarrassed that the project faced so many setbacks.

Mchunu visited the construction site over the weekend to inspect the progress of the project, which was originally due to be completed in June 2017.

It now appears that the completion date will be no later than December, bringing the initial cost of the project from R110 million to R800 million.

Also read: Millions of dollars squandered as Hazelmere dam project stalled after ministry fails to pay

Since construction work to raise the dam wall by 7 meters began in July 2015, delays and setbacks have caused continued disruption, eventually forcing construction company Group Five to halt work in 2018 after the water and sanitation service failed to pay the necessary 40 million rand. purchase specialized materials to complete the job.

The size and scale of the Hazelmere Dam is a sight to behold, clearly illustrated in this photograph of the site visit by Umgeni Water, the Department of Water and Sanitation, Ingerop and Group Five officials .

Things got worse the following year when Group Five moved offsite after terminating its contract with the department.

The ministry suggested the project be put out to tender again, but the Treasury stepped in and Group Five was brought back in October last year.

In December, they had resumed their activities.

The Courier recently reported on the millions of liters of water that were wasted when the structural integrity of the dam wall was compromised, necessitating the release of water.

The stress aspects of the post-tensioned anchors are explained to the Minister of Water and Sanitation, Senzo Mchunu.

Heavy rains have pushed the dam to 62% of its current capacity – already over 100% of its former capacity.

But water had to be released from the dam sporadically to maintain lower capacity levels that would not compromise the integrity of the dam wall.

This resulted in a loss of 11,608 megalitres of water – a single megalitre equals 1 million litres.

The size and scale of Hazelmere Dam is a sight to behold.

When completed, the wall will have been raised 7 metres, stabilized and a piano key weir system (PKW) built in to allow for a free overflow weir which requires far less maintenance than a mechanically operated weir gate .

Post-tensioned anchors were installed using the largest hydraulic ram in the world, specifically commissioned for the Hazelmere Dam project.

While the construction of the PKW and the injection curtain is complete, 10 of the 83 anchors still need to be installed and tensioned.

Raising the wall will increase water availability on the North Coast by approximately 10 million m3 per year to meet the growing needs of the region.

The Hazelmere Dam, located on the Mdloti River, was constructed as a concrete gravity dam in 1975.

The dam supply area extends from KwaDukuza (Stanger) in the north to Groutville, Blythedale, Ballito and Verulam in the south.


For the latest news, follow The North Coast Courier on Facebook, Twitter, instagram and Youtube.

Join our Telegram broadcast service at: https://t.me/joinchat/yJULuN8NaCs5OGM0

Join our WhatsApp broadcast service: Just add 082 792 9405 (North Coast Mail) as a contact on your phone, and WhatsApp your first and last name to the same number to add.